Cables de fibra óptica a través de un pozo vertical
Sinohydro | Israel | 2021
The Challenge
Collahuasi Mine required to transport water that needed to cross mining crossroads, where the pipes where continuously exposed by the heavy trucks that circulate the area.
In the past, the client used HDPE pipes that created a bottleneck on the crossroads. To gain time they reinforced them with steel pipes that acted as steel protectors for the pipes. But still, the solution was very expensive.
The Solution
Since 2012 the client decided to replace all the water HDPE pipes with Pexgol. This change brought several benefits to the company, such us better productivity during the installation of the lines, better performance under harsh conditions, and thanks to its mechanical properties it improved the issues reducing the bottleneck on the crossroads.
The average installation time was reduced from 3-4 days to 4 hours per crossroad. On each one a Pexgol pipe was installed without a sand bed neither a steel protector. It only required a trench and a simple process to compact ground, using the natural field.
Customer:
Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile | 2012
Working conditions:
Extreme environmental temperatures (-25°C to 40°C), 10 bars.
Pipes used:
Pexgol 160 mm, Class 15 (SDR 11).
Application:
Water transport.
Length:
4000 m.