Cables de fibra óptica a través de un pozo vertical
Sinohydro | Israel | 2021
The Challenge
The Chuquicamata mine needed to draw water at the lowest levels of the mine in order to keep it functioning. Commonly HDPE was used for this task, but the client this time required a fast and economical installation; two things that are not possible with this type of material.
The Solution
When this problem arose, the engineering company NBI (Grupo Astaldi), which was in charge of the project, decided to install Pexgol pipes to carry out the drainage.
The pipeline was connected with mechanical couplings to an existing HDPE pipe, which was then hung at 3 meters high with mining bolt supports.
The same activity carried out by HDPE pipes used sections of 12 meters, with mechanical couplings joints, which have greater potential for faults in the line. Thanks to the flexibility and capacity of the Pexgol pipes to be delivered in long stretches, the installation took considerably less time.
Pexgol vs HDPE pipeline performance summary by NBI
Pexgol pipe installation performance (200 meter sections):
Units | Quantity | Time (h) | Effective Time (h) | |
---|---|---|---|---|
Positioning (from the floor to the support) | m | 200 | 16 | 16 |
Alignment (15° slope) | m | 200 | 5 | 5 |
Connections (between pipes) | un | 2 | 7 | 7 |
Joints | un | 2 | 7 | 7 |
Total Hours | 35 | 35 | ||
Total Days | 1.5 | 3 |
Performance of HDPE pipe installation (12 meter sections) with Victaulic joints:
Units | Quantity | Time (h) | Effective Time (h) | |
---|---|---|---|---|
Positioning (from the floor to the support) | m | 12 | 2 | 2 |
Alignment (15° slope) | m | 12 | 2 | 2 |
Connections (between pipes) | un | 2 | 6 | 6 |
Joints | un | 2 | 4 | 4 |
Total Hours (12 m) | 14 | 14 | ||
Total Hours (200 m) | 238 | 238 | ||
Total Days(200 m) | 10 | 20 |
Differential Pexgol vs HDPE pipes by NBI
Uncoiling Process
Installation
Client
Codelco Chuquicamata
Chile| 2017
Working Conditions:
Extreme temperatures -10° to 40°C
Pipes used:
Pexgol 250 Class 19 (SDR 9)
Application:
Mine Dewatering
Length:
1400 meters