Cables de fibra óptica a través de un pozo vertical
Sinohydro | Israel | 2021
The Challenge
At Svetlogorskiy Mill Paper Plant they needed to repair their stainless steel pipes a few times a year, since they were transporting alkali at very high temperature.
The main challenge for the line was the sedimentation issues.
The Solution
The client decided to replace the stainless steel pipes with Pexgol pipes. Thanks to it smooth inner surface, sedimentation is not a problem
and as a consequence requires less maintenance.
The line has been installed since 2015 and it stills shows amazing results.
Stainless Steel Pipe
Pexgol Pipe
Client
Svetlogorskiy Mill
Russia | 2015
Working Conditions:
Non-pressure, high temperature and scrubber water
Pipes used:
Pexgol 160 mm Class 15
Application:
Alkali transportation in caustic and regeneration workshop
Length:
13 m