The Challenge
Antofagasta Minerals faced constant water accumulation at the bottom of the mine, it was interfering with the extraction of the minerals. In addition, the mine operators faced:
The Solution
The installation of a Pexgol’s flexible pipe, which was produced and transported in coils, reducing both installation time as well as the number of joints. Since installation in early 2011, it has been working with no sign of clogging.
The client is fully satisfied with the pipe’s robust performance, including its quick, easy installation and ability to withstand pressures of higher than 24 bars.
Since Pexgol’s pipes require less maintenance than PE pipes and eliminate previous frequent failures, it will be used for many additional applications at the mine.
Customer:
Antofagasta Minerals, Michilla Mine
Chile | 2011
Working conditions:
High pressure (over 24 bar).
Pipes used:
Pexgol 160×27, Class 30.
Application:
Dewatering.
Length:
700 meters.